Sort by *
C
OUR DES
C
OMPTES
Lessons from the
2010 floods on the
Atlantic coast (Xynthia)
and in the Var
July 2012
Disclaimer
Summary
of the
Public Thematic Report
T
his summary is intended to help the reader under-
stand and make use of the Cour des Comptes
report.
The Cour des Comptes is responsible only for the con-
tent of the report.
Responses by government departments, councils and
other organisations are appended to the report.
Contents
3
Summary
of the Public Thematic Report by the
Cour des Comptes
Overview
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
1
Increased and forgotten risks
. . . . . . . . . . . . . . . .
7
2
Early warning and emergency response systems:
further progress needed
. . . . . . . . . . . . . . . . . . . . . .
9
3
Prevention: persistent deficiencies in urban
planning
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
13
4
Protecting built-up areas: a lack of consistency
. .
17
5
Compensation: very comprehensive, but with some
inconsistencies
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
23
Conclusion
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
27
Recommendations
. . . . . . . . . . . . . . . . . . . . . .
29
Overview
5
Summary
of the Public Thematic Report by the
Cour des Comptes
T
wo natural disasters that occurred in 2010 are etched into our memories because of their
dramatic consequences.
Storm Xynthia reached the French coast during the night of 27-28 February 2010,
causing sudden and extensive marine flooding. The human toll was very heavy: 29 deaths con-
centrated in La Faute-sur-Mer in the Vendée and 12 deaths in Charente-Maritime.
On 15 June 2010, the Var was hit by extraordinary floods triggered by overflowing
rivers and run-off, in turn caused by exceptional rainfall. The Draguignan area and the
Nartuby and Argens valleys were particularly hard hit. The death toll was 23, with nine peo-
ple losing their lives in Draguignan; another two people were reported missing.
Hundreds of people also suffered both physical and psychological trauma, losing their
homes and all their belongings.
As well as their tragic human cost, both these disasters resulted in considerable financial
costs to local authorities. Total public expenditure (by central government, local authorities and
Europe) amounted to
467 million for Xynthia and
201 million for the Var floods.
Insurance payouts came to
690 million for the Xynthia floods and
615 million for the Var
floods, making a total of more than
1.3 billion,
640 million of which was covered by the
“natural disaster” government guarantee scheme. Public expenditure is funded by taxes paid
by all taxpayers, while the cost of insurance claims is funded by insurance premiums and the
natural disaster contribution paid by virtually everyone in the country.
These consequences have raised questions over the government’s response, in terms of its
ability to prevent and manage these kinds of disasters.
It is for this reason that the Cour des Comptes and three Chambres Régionales des
Comptes covering the Pays de Loire, Poitou-Charentes and Provence-Alpes-Côte d’Azur
regions carried out a series of audits in 2011, through an interjurisdictional structure, to learn
lessons from these terrible floods.
7
Summary
of the Public Thematic Report by the
Cour des Comptes
Cour des Comptes
1
Increased and
forgotten risks
Increased risks
The disasters affected vulnerable
areas in which urban development
increased the level of risk to the popula-
tion.
Until the mid-20th century, these
areas mainly consisted of farmland
where the principal threat was the risk
of marine flooding along the Atlantic
coast and overflowing rivers in the Var.
Since then, urban development has
changed the nature of the risks. As a
result of demographic pressure, which
is particularly high in coastal areas and
in the southernmost part of the country,
as well as the considerable inflow of
people during the tourist season, and in
spite of limited capacity, there is a real
“thirst” to build in these areas, fuelled
by owners and developers and support-
ed by local elected officials.
The southern Vendée area includes
the
towns
of
La
Faute-sur-Mer,
L’Aiguillon-sur-Mer and La Tranche-
sur-Mer. Its population, which is boost-
ed by 150,000 summer holidaymakers,
has grown by 22% in little more than a
quarter of a century.
Since 1982, the population of
Charente-Maritime has grown by 21%
and that of the Var by 43%. These fig-
ures almost double in the summer, with
the population of Charente-Maritime ris-
ing to almost one million and that of the
Var exceeding two million.
Forgotten risks, in
spite of warnings
There were other disasters before
2010, but they were forgotten. And yet,
some of them left clearly visible traces:
for example, a marble plaque on the wall
of the chemist’s shop opposite the town
hall in Trans-en-Provence is a reminder
of the high water line reached by the
1827 flood and the damage it caused.
Above all, warnings had been given.
For example, a 2008 report emphasised
a serious risk in La Faute-sur-Mer and
L’Aiguillon-sur-Mer posed by “the com-
bination of two phenomena: rising
water levels in the Lay estuary and
marine flooding”, and pointed out that
“ the Lay estuary region is the most dan-
gerous part of the coast…”. While this
report undoubtedly failed to arouse
enough interest, a brochure on the Lay
estuary flood prevention plan, circulated
more widely in July 2007, continued to
describe this alarming state in similar
terms.
Increased and forgotten risks
8
Summary
of the Public Thematic Report by the
Cour des Comptes
In the final analysis, a serious lack of
risk awareness led populations and pub-
lic authorities not to take full measure of
the threats hanging over some areas in
the three
départements
in question.
Steps taken since
these events
As well as generating a large amount
of feedback, the two disasters have been
the subject of parliamentary reports and
inspections.
As a result, the government has
adopted various initiatives grouped
together into a “rapid submersion plan”
(sometimes known as the “plan digues”
or “flood defence plan”), published on
17 February 2011. The plan aims to
deliver a more effective response to
marine flooding, flash floods and
breached flood defences.
It points forward to the national
flood risk management plan, the frame-
work for which was laid down in the
12 July 2010 Act on the national com-
mitment to the environment, known as
“Grenelle 2” , transposing the Euro-
pean Directive of 23 October 2007,
known as the “Floods Directive”. The
purpose of the Directive is to establish
a strategic view of flood risks by 2015.
Certain systems put in place, partic-
ularly in connection with forecasting
and warning, proved their effectiveness
when the Var once again experienced
exceptional rainfall in November 2011.
9
Summary
of the Public Thematic Report by the
Cour des Comptes
Cour des Comptes
2
Early warning and
emergency response
systems: further progress
needed
Early
warning
and
emergency
response systems can save human lives.
They also have a limited cost relative to
their impact in the event of a crisis. To
achieve their purpose, however, they
must be comprehensive, consistent and
rational.
Early warning
systems
Significant improvements
in weather and flood fore-
casting
While Météo France correctly fore-
cast rising water levels, they underesti-
mated the extent of this phenomenon
in the La Rochelle area, with forecasts
putting the flood surge at between
0.80 metres and 1 metre, compared with
an actual high water line of 1.5 metres.
There were known deficiencies in the
forecasting system, such as a lack of
automated tide gauges and observation
stations belonging to the Naval Hydro-
graphical and Oceanographic Depart-
ment (SHOM) around the edge of the
bay of Bourgneuf and the cove of
L’Aiguillon-sur-Mer. These shortcom-
ings, which affected virtually all coastal
areas subject to a high risk of significant
flooding, are regrettable, even if cor-
recting them would only have had an
impact if substantial progress had also
been made on coastal oceanographic
models.
Since Xynthia, work has begun to
improve tools designed to incorporate
coastal developments into forecasting.
However, this work will take time and in
the meantime gaps still remain. Further-
more, the number of parties involved
suggests a need to formally coordinate
the forecasting of marine flooding.
In the Var, rain devastated a relative-
ly small area of 40-50 km
²
around
Draguignan – something Météo France’s
operational forecasting tools were not
able to forecast with a sufficient degree
of precision. Moreover, monitoring of
the Argens and Nartuby rivers – both of
which are classed as high risk – by the
flood prevention service (SPC) was
woefully inadequate. The SPC comes
under the ministry with responsibility
for the environment, which had cut its
investment expenditure.
After the disaster, a substantial
effort was made to improve equipment.
Early warning and emergency response
systems: further progress needed
10
Summary
of the Public Thematic Report by the
Cour des Comptes
This effort needs to be strengthened
and continued.
Further room for
improvement in
early warning
mechanisms
In interpreting early warning mes-
sages in connection with Xynthia, wind-
related danger outweighed the risk of
flooding, with the 1999 storm acting as
the benchmark in collective memory.
There were, however, deficiencies that
need to be highlighted: for example,
Météo France’s failure to include its very
high wave warning procedure (ATFV)
in its weather vigilance procedures, thus
reducing the visibility of these warnings.
This defect has since been corrected.
In the Var, Météo France discussed
whether or not to increase the alert level
to red; in the end, no red alert was
issued, since it was deemed to be too
long after the event. This policy has
since been revised.
For Xynthia, a red alert was issued
to local mayors via automatic telephone
calls and fax messages sent by prefec-
tures. In Charente-Maritime, representa-
tives of the State administration con-
tacted
local
mayors
personally.
Conversely, mayors in the southern
Vendée, where towns were being flood-
ed, did not ensure that an emergency
warning was issued to the prefect, as laid
down in the French General Local
Authorities Code.
In the Var, the impact of warning mes-
sages sent to mayors was reduced by the
fact that no red alert was issued and by
communication difficulties experienced
during the crisis.
Alerts to local populations fell far
short of what was needed. While may-
ors in Charente-Maritime visited the
most vulnerable individuals to warn
them personally, there was no real oper-
ational warning system in place in either
of the two Atlantic
départements
or the
Var. Steps have since been taken: for
example, the three affected towns in the
Vendée are developing warning systems
using sirens, telephone alerts and vehi-
cles equipped with loudspeakers. This
action would nonetheless be more effec-
tive if it was coordinated.
At the national level, Météo France
and the central service for hydrometeo-
rology and flood warning support
(SCHAPI) are developing new informa-
tion systems covering rainfall and river
flooding. The 2008 White Paper on
defence and national security provided
for a new system to warn and inform
local populations. Its implementation,
however, is falling behind, with no con-
crete plans in place at present other than
the cataloguing of sirens and other local
warning mechanisms. Furthermore,
ambiguities over the sharing of respon-
sibility between central government and
local authorities need to be clarified.
Early warning and emergency response
systems: further progress needed
11
Summary
of the Public Thematic Report by the
Cour des Comptes
Organising the
emergency
response
Plans need to be
supplemented and
updated
There were shortfalls in emergency
plans prior to the crisis.
Central government’s “ORSEC”
plans organising the civil security
response had not been updated, and
flood response exercises were non-exis-
tent. While the Var risk analysis and pro-
tection plan (SDACR) considered flood
risk, the plans covering the two
départe-
ments
on the Atlantic coast did not really
address the risk of flooding. This defi-
ciency has since been only partly cor-
rected.
Meanwhile, very few towns had met
the requirement to draw up a local
emergency action plan. Efforts made
since the crisis remain to be completed:
at the end of 2011, of the 55 towns in
Charente-Maritime that were required to
have such a plan, only 25 did; the equiv-
alent figures were 33 out of 69 towns in
the Vendée and 27 out of 47 in the Var.
Furthermore, these plans do not con-
tain a sufficient level of operational detail,
while intermunicipal plans are too scarce
or even non-existent, as is the case in
La Faute-sur-Mer and L’Aiguillon-sur-Mer,
where there is every reason to justify the
need for such plans.
Emergency services: room
for improvement in both
their use and their coordi-
nation
Feedback has underscored the effi-
ciency and dedication of emergency
services, and steps have been taken to
further
improve
their
capability.
However, some questions still remain
unanswered.
Air assets – which are especially
important during crises of this kind –
were used inconsistently from
départe-
ment
to
département
. For example, signifi-
cant use was made of helicopters as
soon as emergency operations began in
the Var and in Charente-Maritime, while
they were used less and later in the
Vendée. Similarly, the degree of coordi-
nation was variable; in the Var, the abil-
ity to coordinate air assets was simpli-
fied by the fact that the département is
home to military schools. Finally, there
were gaps in air-to-ground communica-
tions.
A national air asset plan, to be
implemented locally through defence
and security zones, has yet to be drawn
up.
Unsuitable facilities
Several fire stations were flooded
when the disasters struck: three emer-
gency services centres in Charente-
Maritime; the L’Aiguillon-sur-Mer fire
station in the southern Vendée; and in
the Var, as well as the emergency servic-
12
Summary
of the Public Thematic Report by the
Cour des Comptes
es centre in Les Arcs-sur-Argens, the
local fire and emergency services
department (DDSIS), the main emer-
gency services centre and the
départe-
ment
’s storage facility in Draguignan.
The local operational fire and emer-
gency response centre (CODIS) was
thus taken out of service, and 87 vehi-
cles were lost out of a total of 160 that
were damaged by the disaster in the Var.
Emergency services facilities located
in flood-prone areas need to be closed
or relocated.
Early warning and emergency response
systems: further progress needed
13
Summary
of the Public Thematic Report by the
Cour des Comptes
Cour des Comptes
3
Prevention:
persistent deficiencies in
urban planning
Building
authorisations
with serious
consequences
Of particular note in this regard is
the “Les Voiliers” housing development
in La Faute-sur-Mer. Conversely, after
much hesitation by the State’s represen-
tative, the planned property develop-
ment in the Valescure area of Fréjus was
refused planning permission. These
examples illustrate promoters’ and local
authorities’ desire to develop sites,
ignoring natural risks, as well as the
weakness of the State’s representative in
the face of this desire. Neither verifica-
tions of legality nor the Water Act
appear to have been applied sufficiently
rigorously in such cases.
Beyond having tragic consequences
for human life, the granting of planning
permission in high-risk areas can end up
costing central government dearly, as
shown by the example of the “solidarity
zone” in Aytré, Charente-Maritime.
Failure in
communicating risk
information
The French Environmental Code
affirms citizens’ right to be informed
about major risks. Before the crises,
however, there were numerous short-
comings in this type of information, not
all of which have been remedied.
Risk information
documents
The
departement’s
major risk docu-
ment (DDRM) is drawn up by the pre-
fect. The documents for the three
départements
in question were too general
in nature and had not been updated
within the maximum time allowed by
regulations (five years). Actions initiated
since 2010 to update these documents
and ensure that they address more spe-
cific risks have yet to be completed.
The municipal major risk informa-
tion document (DICRIM) is drawn up
by the mayor. Before the disasters, only
a tiny minority of towns had such doc-
uments, and those that did exist were
Prevention: persistent deficiencies
in urban planning
14
Summary
of the Public Thematic Report by the
Cour des Comptes
barely operational. Since the crises, pre-
fectures have made help available to
towns to draw up these documents.
However, efforts have been hampered
by staff shortages on the ground. In the
Var, two years on from the disaster, only
32 municipal major risk information
documents have been submitted to the
prefecture; virtually all of the
départe-
ment
’s 153 towns should have submitted
such a document.
Flood hazard atlases (AZI), pro-
duced by the State administration, map
out the risks. In the absence of other
more specific or binding documents,
they can also be used to prevent con-
struction in dangerous areas. However,
they first have to be known about and
distributed. While they had been satis-
factorily distributed in the two Atlantic
départements
, the same was not true of
the Var, where the prefect failed to send
out the new generation atlases to mayors
before the disaster struck. It turns out
that these atlases could have been used
to predict the impact of the disaster
quite effectively.
Conversely, the risks mapped out in
atlases distributed on the Atlantic coast
fell well short of the marine flooding
that took place in February 2010. In any
event, local councils had received the
atlases without enthusiasm and they had
hardly been used in reviewing applica-
tions for building permits.
Since 2010, the relevant ministers
have asked prefects to ensure that risk
mapping documents are fully distrib-
uted. Under the European “Floods
Directive” of 2007, risk mapping activi-
ties will have to be stepped up. Such
activities will need to be carefully coor-
dinated by government ministries.
Information for buyers
and tenants
Information for buyers and tenants
(IAL) on the risks affecting a property,
required under the 30 July 2003 Act and
applicable since June 2006, is subject to
serious shortcomings: not all at-risk
areas are covered; information is gener-
ally incomplete and does not take into
account the full extent of risks; prefec-
toral orders and information on govern-
ment websites dedicated to informing
buyers and tenants is not updated; and
there is a lack of precision in the “state-
ment of risks”, which is required by
ministerial order and is appended by
notaries to agreements to sell and deeds
of sale.
While information for buyers and
tenants in the Var was updated by the
central authorities in 2011 following the
audit by the Cour des Comptes, the
same is far from true for the country as
a whole. A specific review of the exist-
ing situation should be drawn up and
the information scheme should be
relaunched.
Flood risk
prevention plans
The flood risk prevention plan
(PPRI) is ordered and adopted by the
Prevention: persistent deficiencies
in urban planning
15
Summary
of the Public Thematic Report by the
Cour des Comptes
prefect following a public inquiry and, in
particular, opinions from the relevant
local councils. In particular, the plan
defines at-risk areas and is binding in
nature, thus serving to control urban
development.
Some situations, however, raise
questions: the way in which the Saint-
Hermentaire area, where the town’s
main emergency services centre was
flooded without warning, was covered
in the Draguignan flood risk prevention
plan; the excessively long and arduous
progress of the Lay estuary flood risk
prevention plan in the Vendée, which
only entered into the pre-implementa-
tion phase some six years after it had
been ordered and, in the end, had not
been adopted by the time storm Xynthia
struck; and the content of the provi-
sions in this plan, which raises questions
in connection with the area located
behind the eastern flood defences in
La Faute-sur-Mer, where the level of
risk appears to have been reduced.
The examples analysed show that
before the crises:
- flood risk prevention plans had not
been ordered for all at-risk areas;
- where such plans had been
ordered, the procedure was often inter-
rupted, as in the Var, or became bogged
down in interminable discussions;
- the vast majority of mayors
opposed the adoption of such plans or
delayed it as long as possible, feeling
that it would hinder their desire to con-
tinue urban development in their towns;
- the State administration – through
its representatives, the prefects – did not
always stand up to pressure from local
elected officials and often acquiesced to
an excessive lengthening of procedures.
In the meantime, the content of
such plans was subject to consultation,
and even negotiation, to ensure that it
would not place too many restrictions
upon the potential for urban develop-
ment, at the expense of the safety of
people and property. Local elected offi-
cials sought to reduce restrictions as far
as possible, and State representatives
often agreed to compromise solutions.
Steps taken since 2010 point to a
renewed desire on the part of central
government to improve the coverage of
at-risk areas – some of which have been
designated as high priority – within a
short timescale. However, local opposi-
tion from both inhabitants and elected
officials has not disappeared altogether.
If the objectives are to be achieved, pre-
fects must adopt a firmer stance in sup-
port of government.
A new policy taking into account cli-
mate change has been laid down for
coastal risk prevention plans. Further-
more, the European “Floods Directive”
is set to introduce substantial changes to
France’s preventive arrangements. This
transitional phase must not be allowed
to result in a slowdown in the efforts
made to map risks and put in place risk
prevention plans.
Prevention: persistent
deficiencies in urban planning
16
Summary
of the Public Thematic Report by the
Cour des Comptes
Urban planning
documents
Many of the areas affected by the
2010 floods were covered by obsolete
urban planning documents that did little
to constrain extended urban develop-
ment. For example, 12 of the 13 affect-
ed towns in the Var had land use plans
that dated back to before 1995, and
seven of these were drawn up earlier
than 1990.
Since the disasters struck, local
authorities have not made any real effort
to replace these plans with new genera-
tion documents aimed at ensuring bal-
anced and sustainable land develop-
ment.
Meanwhile, the relevant ministries
have not taken action to require local
authorities to begin drawing up “territo-
rial consistency plans” or produce local
urban development plans to replace
obsolete land use plans. It would be
advisable for central government to
enact legislation or regulations requiring
local councils to update their urban
planning documents.
Verification of
legality
Prior to 2010, national guidelines
issued to prefects clearly pointed out the
need to ensure that the verification of
legality included, as a priority, checking
urban planning documents and deci-
sions in at-risk areas. At an operational
level, however, checks conducted on
urban planning activities proved very
lax.
Prefectures often blame this state of
affairs on administrative jurisprudence
or staff shortages. While these argu-
ments partly reflect reality, an examina-
tion of sensitive cases reveals that laxity
in checking documents is mainly
explained by a lack of determination at
prefectoral level.
Following the disaster, the prefects
of the affected
départements
showed ini-
tiative in working towards more rigor-
ous verifications, and were issued with
guidelines containing a greater level of
operational detail. However, if there is
to be a lasting improvement in the effec-
tiveness of verifications of legality, the
necessary qualified staff will be needed,
as will, in particular, a clear willingness
at prefectoral level. Prefectoral authority
in this area will be reinforced by backing
from central government.
17
Summary
of the Public Thematic Report by the
Cour des Comptes
Cour des Comptes
4
Protecting built-up areas:
a lack of consistency
Unsuitable public
facilities located on
the sea front or
riverside
Various examples point to the cost
to taxpayers of establishing public facil-
ities in areas subject to flood risk – a risk
which, though well known, was not
taken into account.
In all three
départements
, numerous
camp sites were affected by the disas-
ters; some were in grave danger, like the
“Côte de Lumière” municipal camp site
at La Faute-sur-Mer in the Vendée,
which was also in contravention of the
law, and the three camps sites at Aytré in
Charente-Maritime. In this
département
,
32 camp sites were flooded, with ten of
these submerged to a depth of at least
one metre. In the Var, nine camp sites
had to be closed in summer 2010.
Although the crises forced the
authorities to face up to the need to
strictly apply camping regulations, the
results to date still leave room for
improvement.
High-risk areas:
buying up built
property
In areas exposed to a particularly
high risk, decisions to carry out amica-
ble purchases of homes by the govern-
ment, as practised in “solidarity zones”,
could have formed part of a policy of
“strategic withdrawal” –
i.e. a policy of
not trying to protect areas where it was
not realistically possible to provide ade-
quate protection. However, a lack of
consistency in the application of this
approach limited its effectiveness.
Different methods
followed post-Xynthia and
in the Var
After Xynthia, it is reasonable to say
that central government rushed to
define “solidarity zones” without ade-
quate consultation, leading to large
numbers of protests.
Following further work by expert
assessors and a more in-depth consulta-
tion, it subsequently defined compulsory
Protecting built-up areas:
a lack of consistency
18
Summary
of the Public Thematic Report by the
Cour des Comptes
purchase areas (involving expropriation
of property owners). These compulsory
purchase areas were often smaller than
the previously defined solidarity zones.
Central government’s decision to
purchase homes on an amicable basis
was based on twin objectives of protec-
tion and national solidarity, giving rise to
a high degree of ambiguity. The high
cost of buying homes located outside
compulsory purchase areas (totalling
almost
50 million in the Vendée and
34 million in Charente-Maritime) illus-
trates the hurried nature of the deci-
sions that were made.
If the aim was to protect the popu-
lation living in high-risk areas, amicable
purchases should have been completed
in the more tightly defined compulsory
purchase areas. If, on the other hand,
the principle to be applied was that of
showing national solidarity for victims,
including in cases where compulsory
purchase was not justified in the absence
of a very high level of risk or where less
expensive protection solutions were
available, other methods would have
been more economical.
The example of the Boucholeurs
district (Châtelaillon, Yves) is revealing
of a chaotic process and contradictory
decisions that were unnecessarily costly
for the public purse.
A radically different method was
followed in the Var – rather than imme-
diately defining amicable purchase areas,
the problem was approached in two
phases: the first phase covered 20
homes that had been designated as dan-
gerous structures; the second phase will
include a survey of the most exposed
areas, with properties to be purchased
only in these areas, in consultation with
local elected officials. More than a year
after the events in question, no reliable
estimate of the number of homes con-
cerned was available, though an initial
diagnosis had identified a further 18
homes. Although this procedure avoids
unnecessary purchases, it leads to long
delays to allow for rulings on dangerous
structures, and can make it more diffi-
cult for owners to agree to a sale when
the time comes.
While a slower process has disad-
vantages, the legitimate need for speedy
action does not justify hasty govern-
ment action in the immediate aftermath
of Xynthia.
Funding of property
purchases
Expenditure on buying homes,
which totalled
316 million at end June
2012 in the two Atlantic
départements
, is
funded by the major natural risk preven-
tion fund, commonly referred to as the
“Barnier fund”. This amount accounts
for almost all fund expenditure in the
four-year period from 2006 to 2009
(
331 million). To ensure that the fund
was adequately financed in 2011, the
government had to allocate in advance
the dividend from the Caisse Centrale
de Réassurance (the French state-owned
reinsurance company), as well as agree-
ing another advance to bolster the
Protecting built-up areas:
a lack of consistency
19
Summary
of the Public Thematic Report by the
Cour des Comptes
fund’s cash reserves, which had been
more or less used up by the end of
2010.
The need to define a
policy for properties
exposed to serious danger
There is a risk that the need to pro-
hibit future construction in all or part of
the affected areas might be gradually
forgotten; to avoid this risk, the ultimate
status of properties purchased by gov-
ernment remains to be determined. It is
also essential that dangerous areas else-
where on the coast be identified and
that appropriate action be taken, either
by purchasing relevant properties or by
making them less vulnerable.
Finally, it would be advisable that
local authorities, who share some
responsibility for existing urban devel-
opment, contribute to the cost of pur-
chasing properties at extreme risk, as
this would give them an incentive to take
more care when issuing building per-
mits.
Ultimately, a consistent, overarching
policy covering all at-risk situations still
remains to be defined.
Flood defences
and protection
works
People rely on sea flood defences to
be effective and on their local elected
representatives to effectively manage the
risks associated with rivers. However,
the 2010 disasters highlighted the inade-
quacy of existing arrangements.
Difficulties in identifying
responsible parties
Before the disaster, central govern-
ment took action to identify and classify
sea flood defences in the two Atlantic
departments. This work encountered
serious limitations.
Identifying the parties responsible
for flood defences turned out to be a
very complicated task. In many cases, it
is not known who owns each flood
defence. Where this information is
known, the owners are often found to
be incapable of maintaining flood
defences due to a lack of resources and
willingness. It is also difficult to identify
who is responsible for managing flood
defences. For example, it has not been
possible to identify the parties responsi-
ble for 95% of the total length of sea
flood defences in Charente-Maritime.
Finally, the large number of poten-
tial operators linked to a given stretch of
flood defences creates confusion, mak-
ing it difficult if not impossible to prop-
erly maintain defences.
In the Var, all four of the rivers that
gave rise to the floods are non-govern-
ment owned; this means that the
riverbed belongs to the owners of the
riverbanks, who are, in principle,
responsible for regular maintenance of
the river. Local authorities and groups
of local authorities have the option, but
Protecting built-up areas:
a lack of consistency
20
Summary
of the Public Thematic Report by the
Cour des Comptes
not the obligation, of acting in place of
riverside landowners where a declara-
tion of public interest (DIG) is issued
following a public inquiry.
In reality, the rivers were not main-
tained by riverside landowners, and
intervention by local authorities proved
greatly lacking.
Poorly maintained flood
defences and rivers
In spite of a limited effort following
the 1999 storm, funding for the mainte-
nance of flood defences on the Atlantic
coast was far from sufficient before the
disaster.
Between 2001 and 2009, average
annual expenditure on flood defences in
the three affected towns in the southern
Vendée was
0.54 million; in reality,
three to four times this amount was
needed. Between 2000 and 2009, central
government allocated
8.7 million to sea
flood defence works in Charente-
Maritime; after Xynthia, it committed
19.5 million – 2.2 times more in one
year than the total for the previous ten
years.
Over and above the issue of fund-
ing, the examples of the flood defences
in La Faute-sur-Mer (Vendée) and
Charron (Charente-Maritime) highlight
the difficulty of successfully investing in
flood defences when no one is really
responsible for them. They illustrate the
“vagueness of collective irresponsibili-
ty”, which government failed to remedy.
In the Var, while the Nartuby was
covered by a river contract, the intermu-
nicipal union for the development of
the Nartuby (SIAN), which was respon-
sible for implementing the contract, had
completed very few of the planned
flood protection actions.
Action undertaken since
the disasters
Government-instigated
flood
defence works undertaken post-Xynthia
– including both phase 1 emergency
works and phase 2 upgrading and rein-
forcement works – bore no relation in
financial terms to what had gone before.
Under the “rapid submersion plan”, this
financial effort is set to increase sub-
stantially over the next few years.
Furthermore,
a
draft “flood
defences” decree is being drawn up. In
particular, this decree will be accompa-
nied by an order defining key principles
for the design, construction, mainte-
nance
and
monitoring
of
flood
defences. The process of defining these
technical standards appears to be some-
what belated, and should be completed
without delay.
Under the “rapid submersion plan”,
prefects are tasked with identifying pri-
ority high-risk diked areas and seeking
out project owners for the relevant
flood defences.
The prefects of the two
départements
on the Atlantic coast have been actively
involved, alongside local authorities, in
drawing up flood prevention action pro-
Protecting built-up areas:
a lack of consistency
21
Summary
of the Public Thematic Report by the
Cour des Comptes
grammes (PAPI). However, this process,
while seeking to be rigorous in identify-
ing those responsible for managing
flood defences, is taking time, while
there is a high level of demand for
effective protective measures in exposed
areas. Government authorities must
work with their partners to manage this
difficulty, avoiding protective measures
that would only serve to encourage fur-
ther dangerous urban development.
In the Var, a new desire to ensure
that rivers are properly managed is
reflected in the production of a flood
prevention action programme. Here
again, this process, while positive, will
require time, and interim solutions will
need to be found. Moreover, govern-
ment should initiate discussions on the
subject of legislation and regulations
governing
non-government
owned
rivers to identify which authority can
genuinely take responsibility for their
maintenance.
The unresolved issue of
flood defence governance
In their feedback, government
inspectors considered “three scenarios
to meet the challenge of managing
flood defences”: adjustments to the sta-
tus quo; the transfer of responsibility to
local authorities, intermunicipal bodies
or
départements
; and the creation of a
national managing body.
The “rapid submersion plan” relies
on prefects taking action to identify a
responsible authority, encouraging local
stakeholders to take on the management
of flood defences not owned by them.
While this approach is pragmatic, it is
uncertain whether the funding available
under the plan will be sufficient to con-
vince local authorities to assume a
responsibility that will prove very signif-
icant.
A review of action taken by prefects
should therefore be drawn up, within a
reasonable time frame, so that this
action can be taken into account when
making the (probably legislative) deci-
sions needed to settle the issue of gov-
ernance. The current legal framework is
still governed by the provisions of the
16 September 1807 Act on “drying out
marshland”. The Act, under which resi-
dents are asked to protect themselves
against flooding, bears little resem-
blance to the current environment,
which is characterised by increased
urban development. The focus is no
longer on individuals protecting their
property; it has shifted to the need for a
genuine public service at local or inter-
municipal level.
The fundamental issue of gover-
nance thus remains to be resolved.
Furthermore, the role played by the
natural disaster insurance scheme in
encouraging protective and preventive
action should be affirmed.
23
Summary
of the Public Thematic Report by the
Cour des Comptes
Cour des Comptes
5
Compensation: very
comprehensive, but with
some inconsistencies
Aid and
compensation
Insurance payouts
Although insurers worked hard to
quickly pay compensation to private
individuals, they made little in the way of
specific effort for businesses, while cen-
tral government made aid available to
help businesses get through this difficult
period.
While the average cost per claim in
the Var was slightly lower than that aris-
ing from the Xynthia floods (
16,788
versus
20,909), the cost of compensa-
tion paid to businesses and local author-
ities was higher in the Var (
266.3 mil-
lion versus
208.9 million).
Donations and aid for
private individuals
Total donations received amounted
to
5.65 million for Xynthia and
1.14 million for the Var. Taking into
account 66% tax relief, this represented
a cost to government of
4.4 million.
Local authority procedures for
channelling aid directly to victims, and
the speed with which aid payments were
made, were highly variable, with signifi-
cant differences even between neigh-
bouring towns like La Faute-sur-Mer
and L’Aiguillon-sur-Mer. While not
unusual, differences in the methods
used to redistribute donations can give
rise to misunderstandings, and even
feelings of unfair treatment. It would be
worthwhile for central government to
put together a guide recommending
rules for local authorities to follow
when channelling aid directly to the vic-
tims of these types of disasters.
Furthermore, donations were not
managed in a consistent way. The prob-
lems that occurred – potential for the
duplication of aid, insufficient coordi-
nation, failure to allocate amounts for
their intended purpose and the scatter-
ing of aid – need to be corrected.
Tax deductions and
exemptions
The cost of tax deductions granted
to private individuals was four and a half
times higher in the Var than in the
Vendée, while the cost of compensation
for homes under the natural disasters
scheme was only slightly higher in the
Compensation: very comprehensive,
but with some inconsistencies
24
Summary
of the Public Thematic Report by the
Cour des Comptes
Var than in the Vendée. Furthermore, it
is surprising that the number of
requests was so high, and that all such
requests were accepted. The total direct
cost of tax measures was
1.73 million
for Xynthia and
4.09 million for the
Var.
Property purchase
expenditure
Properties affected
“Solidarity zones” covered 840 prop-
erties in the Vendée (including 11 business-
es) and 788 properties in Charente-
Maritime (including 70 businesses).
In the Vendée, 701 homes, situated
in La Faute-sur-Mer and L’Aiguillon-
sur-Mer, were covered by sale agree-
ments; at end 2011, 699 purchases had
been completed for a total value of
151.5 million. Thirty-three homes, situ-
ated in La Faute-sur-Mer, 17 of which
were secondary residences, had an
assessed
market
value
in
excess
of
500,000, representing a total cost to
central government of
19.3 million.
The highest single purchase cost was
831,000 for a secondary residence.
In Charente-Maritime, 458 proper-
ties in 13 towns were covered by sale
agreements at end 2011, for a total value
of
141.8 million. Eleven homes, eight
of which were main residences, had an
assessed
market
value
in
excess
of
1 million, representing a total pur-
chase cost of
16.65 million.
Problems encountered
Two different procedures were used
for amicable purchases, each of which
had similar aims and terms, thus compli-
cating the task of managers for no gen-
uinely convincing reason.
Tax exemption was granted for cap-
ital gains on secondary residences in the
two Atlantic
départements
, leading to
questions being raised in some cases.
For example, a property situated in
La Faute-sur-Mer was bought for
602,776 after deducting insurance pay-
outs of
173,224, while it had been
bought in December 2007 at a reported
price of
300,000. Work had since been
completed on the property costing
around
90,000. In contrast to what
would have happened in a normal sale,
the purchase of the property by govern-
ment enabled the owner to secure a
completely tax-free capital gain of more
than
300,000.
Most amicable purchases by govern-
ment were based on an article in the
French Environmental Code, which
authorises such transactions provided
that the price “proves less expensive
than the cost of safeguarding and pro-
tecting the population”. While a com-
parison with the cost of other safe-
guarding measures was carried out in
the Var, no such comparison was made
for the Xynthia disaster. No analysis was
undertaken of the situation of each
individual home and, in particular, no
case-by-case checks were carried out to
Compensation: very comprehensive,
but with some inconsistencies
25
Summary
of the Public Thematic Report by the
Cour des Comptes
establish whether other safeguarding
measures would have been less costly.
For those properties that were pur-
chased, checks were not systematically
carried out to establish whether a build-
ing permit had been issued (or whether
retrospective planning permission had
subsequently been granted), depriving
government of a means of dissuading
illegal construction, particularly in areas
at serious risk.
Two properties purchased under
amicable purchase agreements in the
Vendée and one in the Var appeared to
be uninsured. Another property pur-
chased in the Var was only insured after
the event. These were dangerous prece-
dents and were unfair to other home-
owners whose properties were not pur-
chased on the grounds that they were
uninsured.
Insufficient checks were carried out
on insurance payouts, while a basic plau-
sibility check could quite easily have
been conducted. This is all the more
regrettable since the amount of such
payouts is deducted from the amount
paid out by government.
Aid for economic
agents
This type of aid related to farms and
businesses.
It is worth highlighting the
effectiveness of aid provided through
part-time working arrangements.
Government purchases of business
premises, while few in number, raised
difficulties. Blockages and confusion led
to the use of ad hoc solutions based on
procedures that varied from case to
case, thus giving rise to unfair treatment.
The purchase of two restaurants in
L’Aiguillon-sur-Mer, which has been
reviewed in detail, provides an example
of the difficulties and questions raised.
It is advisable that, in the future, the
rules to be applied in this type of situa-
tion be clear and consistent.
Conclusion
27
Summary
of the Public Thematic Report by the
Cour des Comptes
Storm Xynthia and the 2010 Var floods were disasters.
Faced with shortcomings in vigilance, early warning and emergency response procedures, the
progress made since these crises remains to be completed, in particular to create an effective early
warning network. As regards the emergency services, unsatisfactory situations remain, such as fire
stations located in flood-prone areas and a lack of planning covering air assets. Compensation
arrangements, although comprehensive, sometimes proved inconsistent or poorly coordinated.
The post-Xynthia government purchase of many homes in the most dangerous areas gives rise
to numerous comments. The hastiness with which the first decisions were made had serious conse-
quences, based as they were on approximations, compromises, and even regulatory transgressions,
and ultimately led to redundant or unnecessary expenditure. Moreover, the scale of the expenditure
incurred highlighted the cost of negligence and irregularities observed in relation to urban planning.
The wisest approach to protecting human life – and the least costly – is to prevent construction
in undeveloped high-risk areas. In the face of local populations’ desire to build – a desire that is
supported and even encouraged by local elected officials and property developers – State representa-
tives have often proven weak in their preventive response. The burgeoning new determination in this
area needs to be supported by a nationally managed approach to ensure that it is strengthened and
sustained over time.
A strategy for existing built property remains to be defined. Emergency efforts have been made
to repair and consolidate sea flood defences in coastal areas, and the “rapid submersion plan” will
lead to new and more ambitious work in this area. However, priorities need to be made consistent,
with the emphasis on the most dangerous coastal areas and selecting the most effective methods. The
maintenance and reliability of flood defences will only be guaranteed if clearly identified parties take
responsibility for them. However, the issue of their governance is yet to be resolved.
In the Var, there are also glaring shortcomings in governance in relation to rivers; according to
legislation, these rivers, being non-government owned, belong to riverside landowners who have nei-
ther the financial nor the physical means to maintain them. While it is critical than an overarch-
ing strategy be implemented via a flood prevention action programme, this does not obviate the need
for more urgent action in the interim.
In line with the 2007 European framework directive, a national flood risk strategy needs to
be defined, particularly in high-risk areas. The way forward is to map out a consistent strategy, with
measures, an organisational structure and resources appropriate to each at-risk area.
Recommendations
29
Summary
of the Public Thematic Report by the
Cour des Comptes
Early warning
Central government should:
bring overall consistency to
steps taken by towns in relation to
early warning procedures, in coordina-
tion with the future information and
early warning system (SAIP);
ensure that the forecasting of
marine flooding is formally coordinat-
ed;
immediately update risk protec-
tion plans (SDACR) and emergency
response plans (ORSEC) in the most
high-risk
départements
;
put in place an in principle plan
covering the use of national air assets.
Departmental councils and departmental
fire and emergency services in affected areas
should:
close or relocate emergency
services centres situated in flood-
prone areas as quickly as possible.
Towns in affected areas should:
refine and regularly update their
local emergency action plans;
strengthen their early warning
procedures, on an intermunicipal basis
where necessary.
Prevention in relation to urban
planning
Central government should:
lay down a national flood risk
strategy as required by the “Grenelle
2” Act and implement the European
directive on floods, within the stipulat-
ed timescales;
ensure, in implementing the
European directive, that the need to
make changes to existing instruments
does not delay the urgent implementa-
tion of mechanisms agreed upon fol-
lowing the 2010 disasters;
ensure that risk maps are fully
distributed and relaunch the “informa-
tion for buyers and tenants” scheme;
ensure that priority risk preven-
tion plans are implemented within the
stipulated timescales;
ensure that towns have up-to-
date urban planning documents, if
necessary by passing legislation to
require them to do so;
support the prefectoral adminis-
tration in carrying out effective verifi-
cations of legality on urban planning
decisions made by local authorities;
introduce national management,
including targets and regular feedback
from prefects, for the most sensitive
procedures, such as the drawing up and
distribution of risk maps, the imple-
mentation of prevention plans and the
updating of the “information for buy-
ers and tenants” scheme.
Recommendations
30
Summary
of the Public Thematic Report by the
Cour des Comptes
Towns and intermunicipal bodies should:
produce municipal major risk
information documents (DICRIM)
and properly inform the local popula-
tion of risks, in accordance with legis-
lation;
work proactively with the prefec-
toral authority to ensure that preven-
tion plans are rapidly adopted;
replace obsolete land use plans
(POS), particularly in at-risk areas,
with new generation urban planning
documents and implement “territorial
consistency plans” (SCOT).
Protecting built-up areas:
Local authorities and central government
should:
move public service premises
located in flood-prone areas or, where
possible, adapt such premises as
appropriate;
ensure that camping regulations
are strictly enforced.
Central government should:
accurately identify all dangerous
coastal areas and quickly address them;
ensure that local authorities con-
tribute to the cost of purchasing prop-
erties at extreme risk;
after reviewing prefectoral
action in relation to the gover-
nance of flood defences and rivers,
initiate the required legislative changes.
Ensure that funding is made available
and that efforts are sustained;
ensure that the reform of the
“Cat-Nat” natural disaster scheme is
completed as soon as possible, partic-
ularly in relation to premium adjust-
ments for businesses and the exclusion
of properties constructed in breach of
regulations.
The compensation system:
Central government should:
put together a guide defining
procedures for channelling aid directly
to victims;
determine in advance how com-
pensation is to be managed and paid,
including the identification of a coor-
dinating local authority;
merge the two existing proce-
dures governing amicable purchases of
properties at extreme risk, clarifying
their terms and ensuring that they are
strictly enforced, particularly in rela-
tion to building permits;
ensure that central government
aid allocated to towns after this type of
crisis is more closely aligned with actu-
al local budgetary reality.
Recommendations
31
Summary
of the Public Thematic Report by the
Cour des Comptes
Local authorities and central government
should:
organise a joint discussion
process on increasing insurance cover
for properties owned by local authori-
ties;
improve the clarity and efficien-
cy of the help scheme for farmers by
reducing the number of different pro-
cedures and access points used.